This guide provides clear, step-by-step instructions for installing a HydroBlok™ Shower Niche within your shower system. It covers everything from preparing the wall and marking the niche location to sealing, fastening, and finishing. Following these steps ensures a precise, watertight installation that integrates seamlessly with HydroBlok™ wallboard panels. Whether you’re a professional installer or a DIY homeowner, this guide will help you achieve a clean, durable, and waterproof result.

HydroBlok™ Shower Niche Installation Guide

Before Installing Your HydroBlok™ Shower System

Perform a final floor and wall measurement check to ensure all walls are square.
Make any required adjustments before installing your HydroBlok™ shower system.

Installation Tools & Materials Required

  • #2 Robertson or #2 Phillips screwdriver drill bit

  • Tape measure

  • Fine-point marker

  • Level

  • Utility knife with metal ruler or straight edge

  • Cleaning supplies (paper towels, citrus wipes, rags, dustpan, brush)

Important:
Read all related installation guides before beginning. Contact your local dealer if you have any questions about the installation process.

Installation Steps

Step 1: Decide the Size and Placement

Confirm that your HydroBlok™ wallboard is properly installed and ready for the shower niche.
Determine the desired size and location of the niche within your shower wall.

Step 2: Frame the Shower Niche

Locate and mark your wall studs.
The niche must be positioned so that there is a stud on each vertical side to provide full support.

Step 3: Mark Placement on the Wall

Hold the niche in position with its face against the wall.
Use a level to ensure it’s straight, then trace the outline of the niche onto the wallboard using a fine-point marker.

Step 4: Cut the Opening

Horizontal Lines First

Using a utility knife, cut the horizontal lines first.
These guide cuts help ensure the vertical cuts land in the middle of a wall stud on each side.

Step 5: Confirm Stud Location

Double-check that both vertical cuts align with the wall studs before completing the vertical cuts.

Step 6: Dry-Fit the Niche

Insert the niche into the opening to ensure it fits properly.
Make any necessary adjustments before applying sealant.

Step 7: Apply Joint Sealant

Run a ½” continuous bead of HydroBlok™ Joint Sealant along all four inner edges of the wallboard opening.

Step 8: Press-Fit the Niche

Press the niche—right side up—firmly into the opening.
Smooth out any excess sealant using a HYDROBLOK standard putty knife.

Step 9: Install Washers & Screws

Secure the niche with HydroBlok™ washers and screws:

Fastener Placement

  • Place fasteners at each corner and along both vertical seams every 12".

  • Each washer should overlap half on the niche and half on the wallboard.

For Double-Wide Niches

  • Install additional washers and screws at the top and bottom of the center stud and along the horizontal seam.

Step 10: Apply Final Joint Sealant

Apply a final ½” continuous bead of HYDROBLOK Joint Sealant along all four seams.
Smooth it with a straight putty knife to fully cover all washers.
Ensure there is at least 1" of sealant coverage on each side of every seam.

Step 11: Apply Thinset

After approximately one hour (at a room temperature of 18°C / 65°F or higher), the HydroBlok™ Joint Sealant will skin over, and thinset can safely be applied.